PROGRESS REPORTS AND MEETINGS

Bar Chart Progress Report Updating and Submitting Regularly


At monthly intervals after approval of the Plant Manufacture, Delivery and Erection Program Chart, the Contractor shall submit to the Employer updated bar chart programs and precedence critical path analysis networks in triplicate in an approved format indicating the stage reached in the design, ordering of material, manufacture, delivery and erection of all components of plant. In addition the Contractor will compile and submit “S-curves” based upon the approved program indicating programmed and actual percentage completion of the various stages of drawing approval, manufacture, shipping, civil works and erection for each section of the works plus the overall contract.

An updated cash-flow forecast indicating previously forecast and actual, involving levels together with revised future requirements shall be submitted quarterly. A graphical display in the form of an “S-curve” of the actual vs planned payment certification (on & offshore) shall be provided by the Contractor in triplicate on a quarterly basis to supplement the basic cash flow information.

If, during execution of the Contract, the Employer considers the progress position of any section of the work to be unsatisfactory, or for any other reason relating to the Contract, he will be at liberty to call meetings, either in his Head Office or at Site. If required by the Employer, a responsible representative from the Contractor’s works is to attend at the Contractor’s expense such meetings with sufficient authority to issue instructions or effect an alteration in the works to the satisfaction of the Employer.


Access to the Contractor’s and Sub-Contractor’s works is to be granted to the Employers representative at all reasonable times for the purpose of ascertaining progress.

Comments

Popular posts from this blog

Star Delta Starter Line Diagram and Its Working Principle

ELECTRICAL DISTRIBUTION BOARD DB WIRING

EARTH ELECTRODE RESISTANCE MEASUREMENT

SURGE ARRESTERS SPECIFICATION FOR 132 KV & 33 KV LINE

Why Purge System Is Required For Refrigerant and How Does It Operate in Chiller Compressor

STEP AND TOUCH POTENTIAL: REDUCE ELECTRICAL HAZARD AND IMPROVE SAFETY AWARENESS

CURRENT TRANSFORMERS –CT USING

ভুমিকম্পের কল্প কথা

How Economizer Works in Centrifugal Chiller

wazipoint

DMCA protected

The content is copyright protected to wazipoint and may not be reproduced on other websites.