PROGRESS REPORTS AND MEETINGS

Bar Chart Progress Report Updating and Submitting Regularly
At monthly intervals after approval of the Plant Manufacture, Delivery and Erection Program Chart, the Contractor shall submit to the Employer updated bar chart programs and precedence critical path analysis networks in triplicate in an approved format indicating the stage reached in the design, ordering of material, manufacture, delivery and erection of all components of plant. In addition the Contractor will compile and submit “S-curves” based upon the approved program indicating programmed and actual percentage completion of the various stages of drawing approval, manufacture, shipping, civil works and erection for each section of the works plus the overall contract.
An updated cash-flow forecast indicating previously forecast and actual, involving levels together with revised future requirements shall be submitted quarterly. A graphical display in the form of an “S-curve” of the actual vs planned payment certification (on …

wazipoint

DMCA protected

The content is copyright protected to wazipoint and may not be reproduced on other websites.